2(a) The work below ground level including piling and foundation of the Building comprising the said Parcel |
- Foundation works below lowest floor level:
- Stumps
- Piling & Pile caps
- Raft foundation.
|
 |
2(b) The reinforced concrete framework and floor slab of the Parcel. |
- All primary structural elements above lowest floor level including:
- Beams
- Columns
- Suspended slabs
- Structural Walls
- Roof Beams
|
 |
2(c) The walls of the Parcel with door and window frames placed in position. |
- All non-structural wall within parcels
- All party walls inclusive of wall stiffeners
- Timber Door & Window Frames where there are no sub-frames
- All frameworks for dry partitioning excluding lining of partition.
|
 |
2(d) The roofing/ceiling, electrical wiring, plumbing (without fittings), gas piping (if any) and internal telecommunication trunking and cabling to the Parcel. |
- Roof structure, roofing & flashing
- Floor slab soffits & ceiling framing of the said parcel
- Electrical wiring within parcel
- Water piping within parcel
- Sanitary piping within parcel
- Telephone trunking & cabling within parcel
|
 |
2(e) The internal and external plastering of the Parcel. |
- All plastering to walls, soffits, slabs, beam, columns where specified
- Wall tiles & other wall finishes
- Linings, boards and panels to framed partitions
- Floor screeding and/or other floor finishes
- Painting to internal & external walls, floors and ceilings (if any)
|
 |
2(f) The sewerage works serving the Building. |
- Sewerage works including manholes from the building containing the said parcel connected to a completed sewerage treatment system
|
 |
2(g) The drains serving the Building. |
- Drains & Main Drains connected to outfall
|
 |
2(h) The roads serving the Building. |
- Paved Road leading to building containing the said parcel from an existing road.
- Permanent roads around the building containing the said parcel
- Entrance culvert serving the building
- Kerbs
|
 |