2(a) Foundation Works |
Foundation works below lowest floor level:
|
 |
2(b) Ground floor slab, ground floor columns. |
Primary structural elements Ground floor level including:
- Ground beam
- Ground floor slab
- Ground floor columns
|
 |
2(c) First floor slab, roof beam and walls in position Wall Position Upper roofing |
- 1st floor Internal brick wall & party wall in position
- 1st floor setting; of door or window sub-frames or opening
- 1st floor roof beam
|
 |
2(d) Roofing |
- Top roof system installed.
- Top roof truss and roof tiles installed
|
 |
2(e) Internal plastering, electrical conduits (without wiring) and plumbing (without fittings). |
- M & E piping, sleeves in place
- Plastering to walls and other surface
|
 |
2(f) External plastering |
- Plastering external walls
|
 |
2(g) Ceiling, doors and window including glazing, soil drainage, septic tank and lower roofing |
- Door, window in place
- Sanitary wares & fittings
- Ceiling installed
- Lower roofing completed
- Soil drainage and septic tank completed
|
 |
2(h) Driveway, apron, perimeter drain, fencing and gate |
- Concrete to driveway, perimeter drain, apron
- Fencing and gate in place
|
 |
2(i) Painting and physical completion of the said building |